MIAB Ltd. started works on project Wastewater treatment plant Drniš. |
Thursday, 29 October 2015 19:44 | |
MIAB Ltd. participated in the procurement for the construction of Wastewater treatment plant Drniš, and after the selection decision a works contract has been signed.
The project involves construction of complete biological wastewater treatment plant. Hydro mechanical equipment from MIAB production program is foreseen (automatic coarse and fine screens, penstocks, sand-grease trap and clarifier scrapers, septic tanks receiving station, station for sludge dehydration with non clogging screw presses, chemical air scrubber,..). |
Company MIAB Ltd. has completed works on construction of Wastewater treatment plant Rab with size of 24.000 PE. |
Wednesday, 30 September 2015 19:45 | |
Company MIAB Ltd. after successful construction and trial operation, during which proper functioning of the plant was proved, has completed all works related to construction of Wastewater treatment plant Rab with size of 24.000 PE.
After construction was completed during which equipment from MIAB production program has been installed, trial operation was finished successfully during which total functionality by highest standards of World Bank has been proven. |
Završeni radovi na procrpnoj stanici Mirca na otoku Braču |
Monday, 11 August 2014 00:30 | |
There are no translations available. Tvrtka MIAB d.o.o. završila je radove na procrpnoj stanici Mirca na otoku Braču. Procrpnica Mirca namijenjena je povećanju protoka u zapadnom dijelu vodoopskrbnog sustava otoka Brača. Opremljena je sa dvije crpke snage 130 kW upravljanje pretvaračima frekvencije, te ostalom popratnom opremom (elektromotorni zasuni, senzorika tlakova, protoka i slično). |
Završeni radovi na izgradnji Kanalizacijskog sustava Pakoštane-Drage |
Wednesday, 21 May 2014 00:18 | |
There are no translations available. Tvrtka MIAB d.o.o. završila je radove na izgradnji Kanalizacijskog sustava Pakoštane-Drage (Kanalizacijski sustav Biogradske rivijere, dionica III.B). Radovi su uključivali izgradnju 4.200 m cjevovoda (tlačnih i gravitacijskih) kao i izgradnju dvije crpne stanice (građevinski, strojarski i elektrotehnički dio). |